Shingle the other side of the valley the same way.
Roofing a valley with flashing.
Install valley battens on both ends of the roof valley then attach first flashing 3 4 inches over the roof flange and another 3 4 inches over the fascia if any is present.
Fold the top of the flashing over the ridge.
Snap a chalkline 2 to 3 inches past the valley center on the top layer of shingles.
If eaves flashing is used it should cross the valley centerline each way and be installed before the valley underlayment see eaves flashing discussed in roofing underlayment best practices.
Only nail at the edges with only enough nails to.
Next install a 36 inch wide strip of self adhering bituminous membrane in 10 to 15 foot lengths up the valley.
Closed valleys or open valleys.
There are two common methods for completing the flashing of a valley in a shingle roof system.
Ensure ice and water protector has been installed along the valley first.
To splice the pieces add roofing cement to the lower piece and install the upper piece with at least a six inch.
When properly installed w valley flashing will reliably channel run off water down the roof and into the gutter.
Be sure to check local building codes to ensure you have the proper width for your application.
Roof one side of the valley running the shingles across it.
Recommended procedures of basic valley flashing installation.
Now nail this first flashing at both its far ends.
Then install a non corrosive metal valley flashing of 24 minimum width lap successive sheets of metal flashing a minimum of 12 inches and seal laps.
Drip edge metal valley flashing dormer chimney and kickout flashing are types of roof flashing that shed water away from the connections between roofs walls chimneys and other building assemblies.
Cut the bottom edge and fold it down over the drip edge.
Step 6 install the flashing.
Then starting at the base of the.
Stop nailing 6 inches from the center.
Install an underlayment centered in the roof valley.
To understand what makes a valley either closed or open it is important to understand how a valley is constructed.
Make sure to cover the gap at the bottom of the raised ridge.
Remember to caulk the underside of the flashing with a sealant.
One of the details that varies between homes is the method of flashing the valley areas of the roof.
Apply an approximately 3 inch.